In the sequence of actions with CLM virtual machine as below:

  1. Change VE hardware settings, e.g. increase RAM from 2 GB to 4 GB.
  2. Wait until VE changes are applied and it is possible to change the settings again.
  3. Right after step 2, try to change the settings again.

the following message is displayed in CCP:

Configuration is not changed, operation is not scheduled 

When the same operation is re-tried after ~1 hour, the operation succeeds.


CLM provisioning task has been completed on the side of Operations, but the corresponding Change Order is still in "Long Running Operation" status on the side of Billing. The missynchronization between Billing order and OA task statuses is explained in the following article:

KB128756 An order is completed a bit later than the service has actually been provisioned


Wait for the Change Order to get completed and change VE configuration afterwards.

Search Words

configuration is not changed, operation is not scheduled

5356b422f65bdad1c3e9edca5d74a1ae caea8340e2d186a540518d08602aa065 e12cea1d47a3125d335d68e6d4e15e07 956c448bddc7e1f3585373687602379f 6f1456866eed87488c0f02b298a741c0

Email subscription for changes to this article
Save as PDF