How PBA calculates resource overusage amount?

Answer

The details for method of usage/overuse calculation for additive and non-additive resources are provided below:

Additive resource

Overusage = (amount_used - (amount_included + amount_additional) * Duration_Percent) * Overusage_Fee

Non-additive resource

Overusage = (average_amount_used - (amount_included + amount_additional) ) * Duration_Percent * Overusage_Fee

average_amount_used is calculated as the sum of resource usage on each particular day of month divided by the number of day in month:

(Usage on 1st day of month + Usage on 2nd day of month + ... + Usage on last day of month) / Number of days in month

Search Words

resource

overusage

calculate

additive

198398b282069eaf2d94a6af87dcb3ff caea8340e2d186a540518d08602aa065 210d017ddc3a076d22f0f865b1cf0730 92711db0799e8aefe8e51f12dace0496 801221f8cd76fba7300d1e6817c8e08b e12cea1d47a3125d335d68e6d4e15e07

Email subscription for changes to this article
Save as PDF